PROJECTS

Work you can
stand inside

Residential, commercial and industrial builds across the Western Cape. Each one carried from the first drawing through to handover by the same team.

40+BUILDS DELIVERED
18YEARS ON SITE
4SECTORS
7GBCIDB GRADING
7 PROJECTS
COMMERCIAL
PBHS Clubhouse from the field PBHS Clubhouse, cantilevered roof and spectator balcony PBHS Clubhouse, terraces and adjoining works under construction
COMMERCIAL · IN PROGRESS

PBHS Clubhouse

A clubhouse and function space for the Paarl Boys’ High School sports fields on Bergriver Boulevard: a glazed upper level and spectator balcony under a deep cantilevered roof. Built beside fields in use, with phased handover so they stay open through construction.

SCOPEDesign & build
AREATBC
PROGRAMME14 months
LOCATIONPaarl
RESIDENTIAL
Boulevard foundations below Paarl Rock Foundation brickwork with the mountain behind Foundation walls and trenches under the trees Footing trench with reinforcement and blinding Setting out between foundation walls
RESIDENTIAL · IN PROGRESS

Boulevard

A residential development in Paarl, below Paarl Rock. Footings are poured and the face brick foundation walls are up; the build is set to finish in 2027.

SCOPEConstruction
AREATBC
COMPLETION2027
LOCATIONPaarl
AGRICULTURAL
Drakenstein Stud stable block, finished, with the paved approach Drakenstein Stud stable block, gable end and main doors Drakenstein Stud stable block, long elevation with new trees Setting out with the excavator on site Excavating foundations Tipper trucks bringing in fill Building platform before compaction Compacting the building platform Prepared platform below the mountains Platform with service sleeves set out Reinforcement laid for the floor slab Fixing slab reinforcement Concrete columns and face brick walls going up Brickwork with stable door openings
AGRICULTURAL · COMPLETED

Drakenstein Stud

A stable block for Drakenstein Stud, below the Groot Drakenstein mountains: a long, white-plastered barn under a pitched roof, with a Cape Dutch gable and a paved approach. Built from earthworks and a reinforced floor slab through concrete columns and face brick to the finished building.

SCOPEConstruction
AREATBC
PROGRAMMETBC
LOCATIONFranschhoek
RESIDENTIAL
Middag Krans, new face brick wings under the Franschhoek mountains Demolition with the excavator and loader Taking down the old outbuilding Rubble cleared from round the original house The site from above after clearing Setting out the new wing Digging foundation trenches Foundation brickwork and column reinforcement Laying foundation brickwork against the original house Foundation wall running past the original house Preparing the floor inside the original house Damp-proof membrane and mesh before the slab pour Brick wings with roof trusses and steel going in Steel beams framing the mountain view
RESIDENTIAL · IN PROGRESS

Middag Krans

A home below the Franschhoek mountains. The old outbuildings came down, the original house is being opened up and reworked, and the new face brick wings are at roof height with the steel in.

SCOPEConstruction
AREATBC
COMPLETIONTBC
LOCATIONFranschhoek
Gordon Square residential apartments in Paarl RESIDENTIAL APARTMENTS
RESIDENTIAL APARTMENTS · COMPLETED 2023

Gordon Square

Residential apartments in Paarl.

SCOPEProject management
AREA5 600 m²
PROGRAMME16 months
LOCATIONPaarl
RESIDENTIAL
Charletta, face brick gables going up with the roof trusses Shuttering and props for the first-floor slab
RESIDENTIAL · IN PROGRESS

Charletta

A double-storey face brick home in Paarl. The first-floor slab is cast and the gables are up, with the roof trusses going on.

SCOPEConstruction
AREATBC
COMPLETIONTBC
LOCATIONPaarl
COMMERCIAL
Vetscape from the air, with the stables and paddocks behind The finished entrance gable by day The three gables lit at dusk, from the approach path The building at dusk behind the Bouwen site board The glazed gable lit at night Sliding entrance doors and the Vetscape reception
COMMERCIAL · COMPLETED 2025/26

Vetscape

A veterinary practice in the Paarl–Franschhoek valley, among the stables and paddocks: three white-plastered gables, the central one fully glazed in translucent panels over a sliding-door entrance that lights up the building at night.

SCOPEConstruction
AREATBC
COMPLETION2025/26
LOCATIONPaarl / Franschhoek
NEXT

Bring us
the drawing

Send plans or a short description of the site and we will come back with a scope, a programme and a price range within five working days.

Start an enquiry